PROJECT LICENSE ESTIMATE ESTIMATE BID DUE DATE
NEW CHINATOWN/NORTH BEACH CAMPUS   MAIN BUILDING ANNEX BUILDING  
GROUP 6
Invitation to Bid
Pre-Bid Conference Attendees List - Bid Package 3.80
Pre-Bid Conference Attendees List - Bid Packages 6.30, 6.40, 6.50, 6.80
3.80B Electrical/ Fire Alarm/ Security/ AV
Bid Package 3.80

Bid Tabulation
C-7, C-10 $10,232,803 $2,709,686 11/19/2009 at 2:00 PM
6.30 Roofing & Waterproofing
Bid Package 6.30
C-39 $466,225 $186,091 12/01/2009 at 2:00 PM
6.40 Flashing & Sheet metal
Bid Package 6.40
C-43 $37,200 $19,625 12/01/2009 at 2:30 PM
6.50 Framing, Drywall, Insulation, Acoust. Clngs & Firesafing
Bid Package 6.50
B, C-5, C-35, C-9, C-2, C-16, D-63 $4,916,935 $1,221,420 12/01/2009 at 3:00 PM
6.80 Misc. Carpentry & Architectural Woodwork
Bid Package 6.80
B $557,427 $345,807 12/01/2009 at 3:30 PM
 
GROUP 7
Invitation to Bid
3.40B Mechanical C-4, C-20, C-38, C-43, D-62 $5,693,923 $1,172,395 12/08/2009 at 2:00 PM
6.11 Glazing - Interior C-17 $953,290 $90,465 12/15/2009 at 2:00 PM
6.12 Tile & Stone
Bid Package 6.12
C-54 $250,458 $153,843 12/15/2009 at 2:30 PM
6.90 Doors/ Frames/ Hardware B $565,000 $201,800 12/15/2009 at 3:00 PM
7.90 Theatre Equipment N/A N/A $95,000 12/15/2009 at 3:30 PM
 
GROUP 8
Invitation to Bid
6.13 Terrazzo C-54, D-06 $442,805 $140,815 1/05/10 at 2:00 PM
6.60 Landscape C-27 $87,731 $90,465 1/05/10 at 2:30 PM
7.40 Flooring-Miscellaneous C-15 $1,033,963 $137,433 1/05/10 at 3:00 PM
7.50 Paint & Wall Coverings C-33 $429,990 $116,668 1/05/10 at 3:30 PM
 
         
BID ARCHIVE
Construction Contracts Awarded 2002-2009 - Bid Archive
Academic Joint Use Facility - Bid Archive
West Campus Development - Bid Archive
Chinatown/North Beach Campus - Bid Archive
       

 To view files in PDF format. Adobe® Reader is required. To download a copy click here. 

Contact Us   |  CCSF  |  Disclaimer