City College of San Francisco
Facilities Planning & Construction

NEW MISSION CAMPUS
AWARDED CONTRACTS

Up

 

Original Estimate

Bid Due

  Awarded to Amount
Phase 1  Bid Packages:        
1.1  Demolition & Abatement $1,050,000 6/28/05 Cleveland Wrecking Co. $1,394,822
1.2  Dewatering $60,000 7/14/05 Viking Drilling $140,800
1.3  Earthwork $1,200,000 6/28/05 Granite Excavation & Demolition $719,688
1.4  Shoring & Underpinning $800,000 7/19/05 Granite Excavation & Demolition $639,000
1.5  Pedestrian Barrier $80,000 7/14/05 Rubecon General Contracting $104,000
1.6  Structural Shoring $100,000 7/19/05 No Bidders N/A
1.7  Structural Steel & Stairs $5,000,000 7/19/05 Gayle Manufacturing $8,712,000
1.8  Temporary Power and Safe Off $100,000 6/28/05 Morrow Meadows $123,474
Phase 2  Bid Packages:        
2.1  Reinforcing $1,200,000 8/25/05 Pacific Coast Steel, Inc. $1,303,697
2.2  Concrete & Shotcrete $3,000,000 8/25/05 McCarthy Building Co., Inc. $3,349,500
Phase 3  Bid Packages:        
3.1  Metal Decking $520,000 10/20/05 Pacific Erectors, Inc. $643,426
3.2  Waterproofing $220,000 11/01/05 FD Thomas Corp. $243,418
3.3  Elevators $365,000 10/18/05 Ascent Elevators, Inc. $365,000
Phase 4  Bid Packages:        
4.1  Fire Protection $840,000 11/04/05 Transbay Fire Protection, Inc. $989,800
Phase 5  Bid Packages:        
5.1  Mechanical $40,000 11/08/05 No bidders N/A
5.2  Plumbing $40,000 11/08/05 No bidders N/A
5.3  Electrical $4,000 11/08/05 No bidders N/A
5.4  Temporary Heat $90,000 12/08/05 Not awarded N/A
5.5  Underslab Plumbing $130,000 12/08/05 O'Brien Mechanical, Inc. II $258,777
5.6  Underslab Electrical $14,000 12/06/05 Not awarded N/A
Phase 6  Bid Packages:         
6.1   Man Hoist $420,000 2/16/06 No Bidders N/A
6.1   Man Hoist Re-Bid $420,000 3/13/06 Sheedy Hoist                                  $314,946
6.2   Framing, Gypsum Board & Plaster, Bldg A $2,700,000 3/9/06
6.3   Glass Unit Masonry $48,000 3/2/06 John Jackson Masonry $120,129
6.4   Metal Fabrication $800,000 3/2/06 C.E. Toland & Son $2,039,190
6.5   Glazing & Aluminum Panels $1,900,000 4/6/06 Bid Rejected N/A
6.6   Control Joints & Sheet Metal $300,000 3/2/06 Van-Mulder Sheet Metal, Inc. $376,769
6.7   General Works 1 $1,350,000 3/2/06  ISEC, Inc. $1,670,895
6.8   Insulation & Firestopping $310,000 2/16/06 Coast Building Products $227,549
6.9   Sprayed Fireproofing $310,000 2/16/06 Freas Plastering Co. Inc. $309,038
6.10  Coiling & Upward Sectional Doors $90,000 2/16/06 United California Glass and Door $144,740
6.11  Smoke Containment System $100,000 2/16/06 Partition Specialties, Inc. $135,787
6.12  Framing, Gypsum Board & Plaster, Building B $1,500,000 3/9/06 North Bay Drywall & Plastering Inc. $1,682,000
6.13  General Works 2 $400,000 3/2/06 ISEC, Inc. $445,004
Phase 7  Bid Packages:         
7.1   GFRC $200,000 3/2/06 Architectural Facades Unlimited, Inc. $202,114
7.2   Carpentry and Protection $50,000 2/23/06 Rubecon General Contracting, Inc. $70,040
7.3   Doors, Frames, Hardware $800,000 3/2/06 ISEC, Inc. $851,998
7.4   Mechanical $5,200,000 3/14/06 Western Allied Mechanical, Inc.  $6,310,658
7.5   Security $200,000 3/2/06 AEC Alarms $293,800
Phase 8  Bid Packages:         
8.1     Site Concrete $165,000 4/17/06 No Bidders N/A
8.1     Site Concrete Re-Bid $165,000 5/18/06
8.2     Site Utilities $95,000 3/30/06 Andrew M Jordan Inc., dba A&B Construction, Inc. $89,320
8.3     Interlocking Pavers & Cut Stone $60,000 4/18/06 No Bidders N/A
8.4     Landscaping & Irrigation $50,000 5/25/06
8.5     Roofing $635,000 4/17/06 Pioneer Contractors, Inc. $613,180
8.6     Tile $595,000 4/17/06 American Tile & Brick Veneer, Inc. $530,090
8.7     Acoustical Ceiling $490,000 4/17/06 Spacetone Acoustics, Inc. $458,366
8.8A   Resilient Flooring, Building A $1,000,000 4/27/06 H.V. Welker Co., Inc. dba Welker Brothers $807,060
8.8B   Resilient Flooring, Building B $540,000 4/27/06 Pro Installation Inc., dba ProSpectra Contract Flooring

$471,625

8.9     Carpeting $60,000 4/27/06
8.10   Painting – Building A $400,000 4/20/06 KED Construction

$406,245

8.11   Painting – Building B $200,000 4/20/06 Blue Skies Painting $234,000
8.12   Library Theft Protection $45,000 4/18/06 No Bidders N/A
8.13   Casework & Millwork $1,100,000 4/27/06 Dow Diversified, Inc. $778,419
8.14   General Works 3 $ 100,000 5/25/06 Rubecon General Contracting, Inc. $433,540
8.15   Plumbing

$2,600,000

4/20/06 O'Brien Mechanical, Inc. $2,359,875
8.16   Data & Communication $800,000 4/20/06 Cal Coast Telecom $555,698
8.17   Electrical $5,700,000 4/20/06 Cupertino Electric $5,248,769
Phase 9  Bid Packages:         
9.1     Glass and Glazing, Building A

$500,000

5/31/06

C/S Erectors, Inc.

$640,000

9.2     Aluminum Panel System, Building A $450,000 5/25/06 C/S Erectors, Inc.

$595,202

9.3     Storefront, Building A $200,000 5/31/06 C/S Erectors, Inc.

$585,431

9.4     Glass and Glazing, Building B $1,200,000 5/31/06 C/S Erectors, Inc.

$2,389,835

9.5     Exterior Framing and Plaster, Building A $1,000,000 5/25/06 North Bay Drywall & Plastering Inc.

$1,998,820

9.6     Interior Partition Systems, Bldg A Basement – 3rd Flr $1,500,000 5/25/06 North Bay Drywall & Plastering Inc. $1,773,917
9.7     Interior Partition Systems, Building A 4th Floor $200,000 5/25/06 North Bay Drywall & Plastering Inc. $209,650
Phase 10  Bid Packages:         
10.1     Testing and Balance $100,000 7/20/06 National Air Balance Company, Inc. $110,000
10.2     Louvers $120,000 7/20/06 Western Allied Mechanical, Inc. $234,101
10.3     General Works 4 $1,190,000 7/20/06 Rubecon General Contracting, Inc. $1,124,152
10.4     Lab Casework $150,000 7/20/06 ISEC, Incorporated $160,505
10.5     Lead Remediation $100,000 7/20/06 LVI Environmental Services, Inc. $115,734
10.6     Miscellaneous Metals $250,000 7/20/06 C.E. Toland & Son $264,620

 

 

Contact Us   |  CCSF  |  Disclaimer

Send mail to
mlam@ccsf.edu with questions or comments about this web site.
Last Updated: 12/15/2011 mlam