Original Estimate

Bid Due

Awarded to Amount
Bid Issue 1    

 

 

1.1 Demolition $1,432,000 7/19/07 Silverado Contractors, Inc. $1,374,956
1.2 Plumbing Work $690,000 7/19/07 Pribuss Engineering, Inc. $677,060
1.3 Fire Protection Work $536,000 7/19/07 Re-Bid
1.4 HVAC Mechanical Work $2,423,000 7/19/07 Re-Bid
1.5 Electrical and Telecommunications Work $3,936,000 7/19/07 Cupertino Electric $3,265,379
Bid Packages 1-4        
Bid Package 1
1.1A  Exterior Scaffold $496,805 01-17-08 Nor-Cal  $176,292
1.2A  Man/Material Hoist $841,038 01-17-08 Sheedy $826,520
1.3A  Masonry Restoration - For Pre-qualified Subs Only $3,581,900 01-17-08 Rainbow Waterproofing $3,253,867
Bid Package 2
2.1   Rough Carpentry - For Pre-qualified Subs Only $3,030,000 01-28-08 Cal Pacific Construction $2,557,000
Bid Package 3
3.1  Sitework 02-05-08
3.2  Handrails & Metal Railings $256,060 02-05-08 JC Metal, Inc. $258,060
3.3  Finish Carpentry $897,000 02-05-08 Cal Pacific Construction $687,200
3.4  Re-Roofing/Roof Patching $45,553 02-05-08 Lawson Roofing $34,557
3.5  Sheet Metal $68,380 02-05-08 Best Constructing $291,840
3.6  Concrete Restoration 02-05-08
3.7  Painting Work $1,160,000 02-05-08 Blue Skies Painting $917,463
3.8  Ceramic Tile Work $132,000 02-07-08 California Tile Installers $88,611
3.9  Suspended Acoustical Ceiling Systems 02-07-08
3.10 Roof Specialties 02-07-08
3.11 Overhead Coiling Counter Door 02-07-08
3.12 Glass and Glazing $60,542 02-07-08 Best Contracting $170,690
3.13 Wood Flooring Restoration $61,230 02-07-08 HY Flooring & Gameline Painting 31,721
3.14 Linoleum Floor Covering and Carpet Tile $1,083,000 02-07-08 Floortrends $613,993
3.15 Miscellaneous Specialties $128,241 02-07-08 TBD $134,280
3.16 Toilet Partitions $50,000 02-07-08 JH Supplies $47,975
3.17 Signage and Graphics $128,110 02-07-08 Priority Graphics $165,177
3.18 Wheelchair Lifts $47,000 02-07-08 JBD 85,850
Bid Package 4 - For Pre-qualified Subs Only (4.1 - 4.8)
4.1  Concrete $1,285,000 02-15-08 Plant construction $1,171,313
4.2  HVAC Mechanical Work $2,423,000 02-15-08 Allied Heating $2,523,700
4.3  Fire Protection Work 02-15-08
4.4  Door Assemblies $776,461 02-15-08 Rubecon $376,812
4.5  Wood Window Restoration $2,228,268 02-15-08 Peninsula Builders $2,796,978
4.6  Drywall Assemblies/Plaster $2,189,000 02-15-08 RFJ Meiswinkel $1,498,825
4.7  Structural Steel & Metal Fabrication $825,996 02-15-08 JC Metals $784,696
4.8  Nelson Studs 02-15-08
Pre-Qualification
Plant Construction Company L.P. is pre-qualifying subcontractors for the following trade categories:

Concrete/ Rebar
Mechanical/ HVAC Systems
Nelson Studs
Windows
Doors
Fire Sprinklers
Rough Carpentry
Drywall/ Plaster
 
01-03-08

 

Scaffolding
Manlift
Coring for Nelson Studs
Grouted Anchors
 
01-17-08

 

Please contact Steve Shores of Plant Construction at (415) 285-0500 for bid results.