City College of San Francisco
Facilities Planning & Construction
JOHN ADAMS CAMPUS ALTERATIONS
AWARDED CONTRACTS

| |
Original Estimate |
Bid Due |
Awarded to |
Amount |
|
Bid Issue 1 |
|
|
|
|
|
1.1 Demolition |
$1,432,000 |
7/19/07 |
Silverado Contractors, Inc. |
$1,374,956 |
|
1.2 Plumbing Work |
$690,000 |
7/19/07 |
Pribuss Engineering, Inc. |
$677,060 |
|
1.3 Fire Protection Work |
$536,000 |
7/19/07 |
Re-Bid |
|
|
1.4 HVAC Mechanical Work |
$2,423,000 |
7/19/07 |
Re-Bid |
|
|
1.5 Electrical and Telecommunications Work |
$3,936,000 |
7/19/07 |
Cupertino Electric |
$3,265,379 |
|
|
|
|
|
|
Bid Packages 1-4 |
|
|
|
|
|
Bid Package 1 |
|
|
|
|
|
1.1A Exterior Scaffold |
$496,805 |
01-17-08 |
Nor-Cal |
$176,292 |
|
1.2A Man/Material Hoist |
$841,038 |
01-17-08 |
Sheedy |
$826,520 |
|
1.3A Masonry Restoration - For Pre-qualified Subs
Only |
$3,581,900 |
01-17-08 |
Rainbow Waterproofing |
$3,253,867 |
|
|
|
|
|
|
Bid Package 2 |
|
|
|
|
|
2.1 Rough Carpentry - For Pre-qualified Subs
Only |
$3,030,000 |
01-28-08 |
Cal Pacific Construction |
$2,557,000 |
|
|
|
|
|
|
Bid Package 3 |
|
|
|
|
|
3.1 Sitework |
|
02-05-08 |
|
|
|
3.2 Handrails & Metal Railings |
$256,060 |
02-05-08 |
JC Metal, Inc. |
$258,060 |
|
3.3 Finish Carpentry |
$897,000 |
02-05-08 |
Cal Pacific Construction |
$687,200 |
|
3.4 Re-Roofing/Roof Patching |
$45,553 |
02-05-08 |
Lawson Roofing |
$34,557 |
|
3.5 Sheet Metal |
$68,380 |
02-05-08 |
Best Constructing |
$291,840 |
|
3.6 Concrete Restoration |
|
02-05-08 |
|
|
|
3.7 Painting Work |
$1,160,000 |
02-05-08 |
Blue Skies Painting |
$917,463 |
|
3.8 Ceramic Tile Work |
$132,000 |
02-07-08 |
California Tile Installers |
$88,611 |
|
3.9 Suspended Acoustical Ceiling Systems |
|
02-07-08 |
|
|
|
3.10 Roof Specialties |
|
02-07-08 |
|
|
|
3.11 Overhead Coiling Counter Door |
|
02-07-08 |
|
|
|
3.12 Glass and Glazing |
$60,542 |
02-07-08 |
Best Contracting |
$170,690 |
|
3.13 Wood Flooring Restoration |
$61,230 |
02-07-08 |
HY Flooring & Gameline Painting |
31,721 |
|
3.14 Linoleum Floor Covering and Carpet Tile |
$1,083,000 |
02-07-08 |
Floortrends |
$613,993 |
|
3.15 Miscellaneous Specialties |
$128,241 |
02-07-08 |
TBD |
$134,280 |
|
3.16 Toilet Partitions |
$50,000 |
02-07-08 |
JH Supplies |
$47,975 |
|
3.17 Signage and Graphics |
$128,110 |
02-07-08 |
Priority Graphics |
$165,177 |
|
3.18 Wheelchair Lifts |
$47,000 |
02-07-08 |
JBD |
85,850 |
|
|
|
|
|
|
Bid Package 4
- For Pre-qualified Subs Only (4.1 - 4.8) |
|
|
|
|
|
4.1 Concrete |
$1,285,000 |
02-15-08 |
Plant construction |
$1,171,313 |
|
4.2 HVAC Mechanical Work |
$2,423,000 |
02-15-08 |
Allied Heating |
$2,523,700 |
|
4.3 Fire Protection Work |
|
02-15-08 |
|
|
|
4.4 Door Assemblies |
$776,461 |
02-15-08 |
Rubecon |
$376,812 |
|
4.5 Wood Window Restoration |
$2,228,268 |
02-15-08 |
Peninsula Builders |
$2,796,978 |
|
4.6 Drywall Assemblies/Plaster |
$2,189,000 |
02-15-08 |
RFJ Meiswinkel |
$1,498,825 |
|
4.7 Structural Steel & Metal Fabrication |
$825,996 |
02-15-08 |
JC Metals |
$784,696 |
|
4.8 Nelson Studs |
|
02-15-08 |
|
|
|
|
|
|
|
|
Pre-Qualification |
|
|
|
|
Plant Construction Company
L.P. is pre-qualifying subcontractors for the following trade categories:
Concrete/ Rebar
Mechanical/ HVAC Systems
Nelson Studs
Windows
Doors
Fire Sprinklers
Rough Carpentry
Drywall/ Plaster
|
|
01-03-08 |
|
|
Scaffolding
Manlift
Coring for Nelson Studs
Grouted Anchors
|
|
01-17-08 |
|
|
|
|
|
|
|
|
Please contact Steve Shores of Plant Construction at
(415) 285-0500 for bid results. |
|
|