NEW WEST CAMPUS RESERVOIR SITEWORK
AWARDED CONTRACTS

Up

 

Original Estimate

Bid Due

Awarded to Amount
OCEAN AVENUE CAMPUS
BALBOA RESERVOIR SITE DEVELOPMENT
Phase 1
   

 

 

1.1  Geothermal System, horizontal piping, trenching and backfill $4,500,000 04-25-08, 2:00 P.M. ProVen Management, Inc. $ 4,789,424
1.2  Grading and Backfill for Joint Use Facility and Area West of Joint Use Facility $600,000 05-02-08, 2:00 P.M. ProVen Management, Inc. $ 2,221,062
1.3  Abatement and Demolition of Gymnasiums and Dance Studio $1,500,000 04-16-08, 2:00 P.M. Silverado Contractors, Inc $ 1,049,890
1.4  Construct 2 new parking lots +/- 70,000 SF total at East Campus $700,000 04-16-08, 2:00 P.M Ghilotti Brothers, Inc., $ 326,500
OCEAN AVENUE CAMPUS
NEW WEST CAMPUS RESERVOIR SITEWORK
Phase 2
   

 

 

2.1  Lee Avenue Site Utilities $1,800,000 11-12-08, 3:00 PM A & B Construction $1,299,200
2.2  Phelan Avenue Site Utilities $750,000 11-12-08, 3:00 PM Synergy $731,676
2.3  Phelan Ave Site Temporary and Permanent Power and Central Utility Plant Electrical Distribution $1,450,000 11-12-08, 2:00 PM ProVen Management, Inc. $1,220,063
2.4  Site Power Distribution from The Joint Use Facility to the Other Buildings $500,000 11-12-08, 2:00 PM ProVen Management, Inc. $455,625
2.5   Low Voltage Connection East of Phelan Ave to the Joint Use Facility $125,000 11-12-08, 2:00 PM ProVen Management, Inc. $165,500
2.6  Low Voltage Site Distribution from the Joint Use Facility to other Buildings $400,000 11-12-08, 2:00 PM ProVen Management, Inc. $269,134
2.7  Central Plant Mechanical Equipment, Connections, and Site Distribution Piping $7,800,000 11-12-08, 3:00 PM ProVen Management, Inc. $7,764,714
OCEAN AVENUE CAMPUS
BALBOA RESERVOIR SITE DEVELOPMENT
Phase 2
       
2.8 Concrete Curbs, Gutters, and Ramp $1.200,000 4/10/09, 3:00 PM
2.9 Concrete Stairs, ramps, curbs, metal rails, lighting conduit and base, and irrigation sleeves $1.300,000 4/10/09, 3:00 PM
2.10  Low Voltage Connection to East Campus $200,000 11/9/2009 at 9:00 AM Bid Cancelled
2.10  Site Lighting $400,000 4/8/2010 at 2:00 PM
Request for Quotation - Light Poles 4/5/2010 at 3:00 PM
Request for Quotation - Light Fixtures 4/5/2010 at 2:00 PM
2.11  Parking, Pathways and Misc. Landscape $650,000 5/12/2010 at 9:00 AM

 