City College of San Francisco
Facilities Planning & Construction
CHINATOWN / NORTH BEACH CAMPUS
AWARDED CONTRACTS

| |
Original Estimate
MAIN BUILDING |
Original Estimate
ANNEX BUILDING |
Bid Due Date |
Awarded to |
Amount |
|
GROUP 1 |
|
|
|
|
|
|
Invitation to Bid |
|
|
|
|
|
1.10 Glazing, Metal Panel, Louvers - Exterior
Bid
Tabulation |
$7,892,166 |
$749,565 |
10/8/09 at 2:00 PM |
Architectural Glass & Aluminum |
$9,572,542 |
3.10 Glass Fiber Reinforced Concrete (GFRC) Panels
Bid
Tabulation |
$2,224,660 |
$1,037,855 |
10/8/09 at 3:00 PM |
Re-bidding |
|
3.30 Basement Waterproofing
Bid
Tabulation |
$510,072 |
$221,524 |
10/6/09 at 3:00 PM |
Blue's Roofing |
$702,900 |
3.60 Elevators
Bid
Tabulation |
$2,572,000 |
$835,000 |
10/6/09 at 3:30 PM |
ThyssenKrupp |
$3,654,180 |
4.30 Tower Crane for Main Building
Addendum 1 |
$750,000 |
N/A |
Combined with Bid Package 5.10 |
|
|
5.10 Concrete - Place and Finish, Form & Re-Bar (Main)
Bid
Tabulation |
$9,355,434 |
N/A |
10/14/09 at 2:30 PM |
Webcor Concrete |
$11,587,827 |
5.40 Concrete - Place and Finish, Form & Re-bar (Annex)
Bid
Tabulation |
N/A |
$2,630,876 |
10/8/09 at 2:30 PM |
RJS & Associates |
$3,558,506 |
3.20B Shoring & Mass Excavation (Lot 5 Only)
Bid Tabulation |
N/A |
$746,528 |
10/8/09 at 2:30 PM |
Tucker Engineering |
$1,078,597 |
|
|
|
|
|
|
|
GROUP 2 |
|
|
|
|
|
Invitation to Bid
Pre-Bid Conference Attendees List - Bid Packages
3.70, 3.80
Pre-Bid Conference Attendees List - Bid Packages
5.14, 8.11, 8.14 |
|
|
|
|
|
3.70 Plumbing
Bid Package 3.70
Bid Tabulation |
$2,425,534 |
$759,665 |
10/12/09 at 2:00 PM |
O'Brien Mechaincal |
$3,793,000 |
3.80 Electrical/ Fire Alarm/ Security/ AV
|
$10,232,803 |
$2,709,686 |
10/12/09 at 2:30 PM |
This Bid Package is Re-bidding - See Group 6 |
|
5.14 Professional Survey
Bid Package
5.14
Bid Tabulation |
$140,331 |
$40,064 |
10/15/09 at 2:00 PM |
KCA Engineers |
$157,200 |
8.11 General Labor – Phase 1
Bid Package
8.11
Bid Tabulation |
$187,500 |
$62,500 |
10/15/09 at 2:30 PM |
RT Western Maintenance |
$256,925 |
8.14 Security – Access System/ Guards
Bid Package
8.14
Bid Tabulation |
$491,373 |
$163,791 |
10/15/09 at 3:00 PM |
McCoy's Patrol |
$487,622 |
|
|
|
|
|
|
|
GROUP 3 |
|
|
|
|
|
Invitation to Bid
Pre-Bid Conference Attendees List - Bid Packages
3.40, 4.20. 5.70, 5.80 |
|
|
|
|
|
3.40 Mechanical
Bid Tabulation |
$5,693,923 |
$1,172,395 |
10/20/09 at 2:00 PM |
This Bid Package is Re-bidding - See Group 7 |
|
4.20 Personnel & Material Hoist
Bid Package
4.20
Bid Tabulation |
$1,170,000 |
$650,000 |
10/20/09 at 2:30 PM |
Clipper International |
$1,315,176 |
5.70 Structural Steel
Bid Package
5.70
Addendum 1
Bid Tabulation |
$437,421 |
$126,300 |
10/20/09 at 3:00 PM |
Kwan Wo Ironworks |
$1,152,900 |
5.80 Metal Stairs, including Arch. Stairs
Bid Package
5.80
Bid Tabulation |
$495,000 |
$203,500 |
10/20/09 at 3:30 PM |
Beck Steel |
$827,534 |
|
|
|
|
|
|
|
GROUP 4 |
|
|
|
|
|
|
Invitation to Bid |
|
|
|
|
|
3.11 Building Management
System (BMS)
Bid Package
3.11
Bid Tabulation |
$653,158 |
$172,959 |
10/27/09 at 2:00 PM |
Syserco |
$840,826 |
3.50 Fire Protection
Bid Package
3.50
Bid Tabulation |
$1,089,380 |
$198,613 |
10/27/09 at 2:30 PM |
Cosco Fire Protection |
$1,344,867 |
5.13 Food Service
Equipment
Bid Package
5.13
Bid Tabulation |
$11,600 |
$723,650 |
10/27/09 at 3:00 PM |
East Bay Restaurant Supply |
$803,367 |
|
GROUP 5 |
|
|
|
|
|
Invitation to Bid
Pre-Bid Conference Attendees List - Bid Packages
5.11, 5.12, 6.10, 6.20 |
|
|
|
|
|
5.11 CMU (Interior and Exterior)
Bid Package
5.11
Bid
Tabulation |
$162,680 |
$293,825 |
11/17/09 at 2:00 PM |
Spencer Masonry |
$520,000 |
5.12 Window Washing, embeds & equip
Bid Package 5.12
Addendum 1
Bid
Tabulation |
$450,000 |
N/A |
11/17/09 at 2:30 PM |
Scaffold Inspection & Testing Co. |
$398,898 |
6.10 Misc. & Ornamental Metal
Bid Package 6.10
Bid
Tabulation |
$811,080 |
$169,445 |
11/17/09 at 3:00 PM |
T.C. Steel |
$1,305,874 |
6.20 Laboratory Equipment
Bid Package
6.20
Bid
Tabulation |
$229,460 |
N/A |
11/17/09 at 3:30 PM |
This Bid Package is Re-bidding - See Group 10 |
|
|
GROUP 6 |
|
|
|
|
|
|
Invitation to Bid |
|
|
|
|
|
3.80B Electrical/ Fire Alarm/ Security/ AV
Bid
Tabulation |
$10,232,803 |
$2,709,686 |
11/19/2009 at 2:00 PM |
Cupertino Electric |
$12,448,769 |
6.30 Roofing & Waterproofing
Bid
Tabulation |
$466,225 |
$186,091 |
12/15/2009 at 2:00 PM |
Blue's Roofing |
$963,930 |
6.40 Flashing & Sheet metal
Bid
Tabulation |
$37,200 |
$19,625 |
12/15/2009 at 2:30 PM |
Van-Mulder Sheet Metal |
$592,720 |
6.50 Framing, Drywall, Insulation, Acoust. Clngs & Firesafing
Bid
Tabulation |
$4,916,935 |
$1,221,420 |
12/10/2009 at 3:00 PM |
J&J Acoustics |
$5,812,780 |
|
6.80 Misc. Carpentry & Architectural Woodwork |
$557,427 |
$345,807 |
12/15/2009 at 3:30 PM |
This Bid Package is Re-bidding - See Group 11 |
|
|
GROUP 7 |
|
|
|
|
|
|
Invitation to Bid |
|
|
|
|
|
3.40B Mechanical
Bid
Tabulation |
$5,693,923 |
$1,172,395 |
12/8/2009 at 2:00 PM |
Control Air North |
$4,796,000 |
6.11 Glazing - Interior
Bid
Tabulation |
$953,290 |
$90,465 |
12/22/2009 at 2:00 PM |
Architectural Glass & Aluminum |
$787,400 |
6.12 Tile & Stone
Bid
Tabulation |
$250,458 |
$153,843 |
12/22/2009 at 2:30 PM |
KZ Tile |
$760,000 |
6.90 Doors/ Frames/
Hardware
Bid
Tabulation |
$565,000 |
$201,800 |
1/12/2010 at 3:30 PM |
Boyett Doors |
$1,179,000 |
7.90 Theatre Equipment
Bid
Tabulation |
N/A |
$95,000 |
1/7/2010 at 3:00 PM |
Jezet |
$139,975 |
|
GROUP 8 |
|
|
|
|
|
|
Invitation to Bid |
|
|
|
|
|
6.13 Terrazzo
Bid
Tabulation |
$442,805 |
$140,815 |
1/12/2010 at 2:30 PM |
Re-bidding |
|
7.40
Flooring-Miscellaneous
Bid Package
7.40
Bid
Tabulation |
$1,033,963 |
$137,433 |
1/5/2010 at 3:00 PM |
Re-bidding |
|
7.50 Paint & Wall
Coverings
Bid
Tabulation |
$429,990 |
$116,668 |
1/12/2010 at 4:00 PM |
A&B painting |
$502,557 |
|
GROUP 9 |
|
|
|
|
|
Invitation to Bid
Pre-Bid Conference Attendees List - Bid Package
7.70, 7.10, 7.20, 7.60 |
|
|
|
|
|
7.10 Specialties, T. Part.
& Acces., Lockers, Mailboxes & Payphones
Bid
Tabulation |
$304,595 |
$111,100 |
1/7/2010 at 2:30 PM |
ISEC |
$663,068 |
7.20 Curb, Gutter,
Pavement Striping, etc.
Bid Package
7.20
Addendum
1
Addendum 2
Addendum 3
Addendum
4
Addendum
5
Bid Tabulation |
$55,125 |
$52,770 |
3/23/2010
at 2:30 PM |
Re-bidding |
|
|
7.11 Projection Screens |
$120,000 |
$15,000 |
1/7/2010 at 3:00 PM |
Included in Bid Package 7.10 |
|
7.60 Signage including
Directories
Bid
Tabulation |
$124,085 |
$96,200 |
1/12/2010 at 3:00 PM |
Hackley Architectural Signage |
$159,683 |
7.70 Window Coverings
Bid Package
7.70
Addendum
1
Bid Tabulation |
$367,245 |
$78,955 |
2/5/2010
at 2:30 PM |
Re-bidding |
|
|
|
|
|
|
|
|
GROUP 10 |
|
|
|
|
|
Invitation to Bid
Pre-Bid Conference Attendees List - Bid Package
3.10, 6.20, 7.80, 8.12, 8.13, 8.15 |
|
|
|
|
|
3.10 Glass Fiber
Reinforced Concrete (GFRC) Panels
Bid Package
3.10
Addendum
1
Bid
Tabulation |
$2,224,660 |
$1,037,855 |
1/15/2010 at 3:00 PM |
Willis Construction |
$2,285,000 |
6.20 Laboratory Equipment
Bid Package
6.20
Bid
Tabulation |
$229,460 |
N/A |
1/7/2010 at 4:00 PM |
ISEC |
$354,247 |
7.80 Final Cleaning
Bid Package
7.80
Bid
Tabulation |
$94,610 |
$217,439 |
1/12/2010 at 2:00 PM |
Clean Innovation |
$126,000 |
8.12 General Labor – Phase
2
Bid Package
8.12
Bid
Tabulation |
$187,500 |
$62,500 |
1/12/2010 at 2:30 PM |
John Bertoldi, Inc. |
$256,974 |
8.13 General Labor – Phase
3
Bid Package
8.13
Bid
Tabulation |
$187,500 |
$62,500 |
1/12/2010 at 3:00 PM |
John Bertoldi, Inc. |
$256,974 |
8.15 General Labor –
Elevator Operators
Bid Package
8.15
Bid
Tabulation |
$230,957 |
$57,739 |
1/12/2010 at 3:30 PM |
Clipper International |
$293,280 |
|
GROUP 11 |
|
|
|
|
|
Invitation to Bid
Pre-Bid Conference Attendees List - Bid Package 6.80 |
|
|
|
|
|
6.80 Misc. Carpentry & Architectural Woodwork (Re-bid)
Bid Package 6.80
Bid Tabulation |
$2,101,701 |
Included in Main Estimate |
2/5/2010 at 2:00 PM |
Re-bidding |
|
|
GROUP 12 |
|
|
|
|
|
Invitation to Bid
Pre-Bid Conference Attendees List - Bid Package 6.60,
6.13, 7.40 |
|
|
|
|
|
6.60 Landscape
Bid Package
6.60
Addendum
1
Addendum
2
Bid Tabulation |
$87,731 |
Included in Main Estimate |
3/23/2010
at 2:00 PM |
Re-bidding |
|
6.13 Terrazzo
Bid Package
6.13
Bid Tabulation |
$1,243,200 |
Included in Main Estimate |
2/26/2010
at 2:30 PM |
Re-bidding |
|
7.40
Flooring-Miscellaneous
Bid Package
7.40
Addendum
1
Bid Tabulation |
$1,033,963 |
$137,433 |
3/4/2010
at 2:00 PM |
|
|
|
GROUP 13 |
|
|
|
|
|
Invitation to Bid
Pre-Bid Conference Attendees List - Bid Package
6.80, 6.13 |
|
|
|
|
|
6.80
Misc. Carpentry & Architectural Woodwork
Bid Package
6.80
Bid Tabulation |
$2,101,701 |
Included in Main Estimate |
4/9/2010
at 2:00 PM |
|
|
6.13
Terrazzo
Bid Package
6.13
Bid Tabulation |
$1,243,200 |
Included in Main Estimate |
4/9/2010
at 2:30 PM |
|
|
|
GROUP 14 |
|
|
|
|
|
|
Invitation to Bid |
|
|
|
|
|
6.60 Landscape
Bid Package
6.60
Bid
Tabulation - Bid Package
6.60 |
$110,000 |
|
2/24/2011 at 2:00 PM |
|
|
7.20 Curb, Gutter,
Pavement Striping, etc.
Bid Package 7.20
Addendum 1
Bid
Tabulation - Bid Package
7.20 |
$350,000 |
|
3/10/2011 at 2:30 PM |
|
|
|
|
|
|
|
|
|